Find all the economic and financial information on our Orishas Direct application to download on Play StoreAkrake Petroleum, an indirect subsidiary of
Rex International announced on Monday, January 12, 2026 that it plans to launch
production on the Sèmè field, off the coast of Benin, at the end of the month of
January 2026.
After several weeks of uncertainty,
the Sèmè offshore oil project is being finished.The work must, according to the
press release from the company, the work will begin at the beginning of the week of
January 12. Production is still subject to the completion of drilling
of the AK-2H production well.
Akrake Petroleum, an indirect subsidiary of
Rex International, plans to launch production on the Sèmè field, in
off the coast of Benin, at the end of January 2026. Akrake has a 76% stake
in this block, while the Beninese government owns 15% and the company
local oil company Octogone Trading owns 9%. The announcement was made on Monday 12
January and marks a turning point after the initial calendar was postponed, which aimed to
a start before the end of 2025.The start of production remains
subject to the completion of the drilling of the AK-2H production well.
According to the company, the operations
were slowed down by geomechanical difficulties in the layers of
unstable shales located above the reservoir, causing several
technical incidents and re-drilling. It says
that exploiting new data
geomechanics collected during the work made it possible to adjust the parameters
of drilling and crossing these complex areas when drilling the AK-2H well.
”, serif">
Meeting the end of January deadline will depend on the completion of the drilling of the AK-2H well without further incident major. The first production plateau should be around 15,000 barrels. per day. Data from the AK-1P exploration well must also make it possible to assess the potential of deeper layers, likely to extend the operating life of the field and increase production to medium
Term
Vous devez être membre pour ajouter un commentaire.
Vous êtes déjà membre ?
Connectez-vous
Pas encore membre ?
Devenez membre gratuitement
02/03/2026 - Matières Premières
02/03/2026 - Matières Premières
02/03/2026 - Matières Premières
02/03/2026 - Matières Premières
27/02/2026 - Matières Premières
27/02/2026 - Matières Premières
27/02/2026 - Matières Premières
27/02/2026 - Matières Premières
26/02/2026 - Matières Premières
02/03/2026 - Matières Premières
02/03/2026 - Matières Premières
02/03/2026 - Matières Premières